The skip was finally emptied. We had a meeting with the architects yesterday and they then arranged a meeting with Steve to discuss our concerns. Lots of activity - Clive could now clear the cumulated piles of rubble and dig the trench for the drains, Steve did the false ceiling in the kitchen, the electricians completed the first fix in the kitchen and garden room and the CamTile completed the tiles - just ridge and flashings to do.
So we have progress now and a new plan from Steve - 4 extra weeks - but compressing 9 weeks from the original plan into 6. The new finishing date of the 14th October looks very optimistic. According to http://www.companycheck.co.uk/. Steve has along list of defunct companies associated with him and Inspire has only been registered since Jan 2010.